Heads at Saaremaa Laevakompanii were worried about the new operator about to lure their current staff. «Good mariners will always land a job, and sooner or later the new operators will have to seek out the experienced guys anyway,» said Saaremaa Laevakompanii CEO Tõnis Rihvk.
He explained that sailing the islands to mainland route is complex above average as featuring many manoeuvres and berthing operations. «Like at the Kuivastu-Virtsu line they berth 32 times a day,» he said. «For a captain with little experience, this may spell knocks costing tens of thousands of euros – not all men can work under such conditions and it will be seen in practice.»
As for the ferries built for TS Laevad in Turkey, both vessels are slightly ahead of schedule and with economic conditions continually the usual, deviations are not to be feared.
Representatives of Polish shipyard declined to comment.
Tarvi-Carlos Tuulik, captain at Tallink
While ship building is planned long ahead, being late and later technical issues cannot be excluded. Let’s be honest, we have had stuff like that happen – like subcontractor supplies being late, and work arrangements.
And none is exempt from force majeure – like at an Italian shipyard strong winds bended a crane while Superstar was built so the work was halted unto replacement cranes were found, able to lift the required 500 tonnes of weight.
The testing under government representatives and international classification supervisors is strict, but statistically technical glitches do appear while in regular service due to human errors or low defects in materials used.